Renovating a condo or a rental unit is a different project from remodeling the house you live in. The HOA has a say in your flooring, your contractor's insurance and the hours the crew can work, materials ride up in an elevator, and if the unit is an investment the right finish level is set by the rent it can earn rather than by taste. We get this request every week from Seattle and Eastside landlords, many of them living out of state, who want a durable, clean, mid-range renovation with an itemized bid and reliable communication. This guide gives 2026 planning numbers for a cosmetic turnover, a landlord-grade full interior renovation, an owner-occupied condo remodel and a full gut, line-item prices for cabinets, counters, bathrooms, LVP and paint, what Seattle and Bellevue HOAs and permit offices require, whether to buy your own materials, how long each takes and how to scope the work so it pays back.
The short answer
In 2026, a landlord-grade turnover renovation of a one-bedroom condo or apartment in Seattle, Bellevue or Kirkland (new mid-range kitchen cabinets, counters, sink and appliances, a refreshed bathroom with new vanity, toilet and fixtures, LVP flooring throughout, and full interior paint) typically costs $28,000 to $50,000 when the walls, plumbing stacks and electrical panel stay where they are. A cosmetic rental refresh (paint, flooring, hardware, lighting, a reglazed tub) runs $8,000 to $18,000, and a full gut of a one- or two-bedroom condo with a new layout, relocated plumbing or electrical upgrades lands at $75,000 to $150,000 or more. Per square foot, Washington contractors publish $80 to $150 for cosmetic work, $160 to $275 for a mid-range full renovation and $300 to $500+ for a gut, and condos sit toward the top of each band because of HOA rules, elevator access and sound-rated flooring. These are planning ranges, not quotes: a fixed, itemized price comes after a site visit.
Condo and rental renovation cost by scope
- Cosmetic turnover: $8,000 to $18,000. Two coats of paint on walls, ceilings, doors and trim, new LVP over the existing subfloor, new lighting, outlets and switches, cabinet hardware, a reglazed tub and a new toilet. No cabinets, counters or plumbing moved. Typically 1 to 2 weeks.
- Landlord-grade full interior renovation (1 bed / 1 bath): $28,000 to $50,000. The scope most out-of-area owners ask us for: pull-and-replace kitchen with stock or RTA cabinets, quartz or solid-surface counters, undermount sink and faucet, stainless appliance package, new bathroom vanity, toilet, lighting and fixtures, LVP throughout, baseboards and trim repaired or replaced, full repaint, plus the drywall, plumbing and electrical repairs that show up during demolition. 4 to 7 weeks.
- Mid-range owner-occupied condo remodel (2 bed / 2 bath): $60,000 to $110,000. Semi-custom cabinets, tile backsplash, tiled shower in place of a tub, built-in closet systems and better lighting design, still inside the existing layout. 6 to 10 weeks.
- Full gut or layout change: $75,000 to $150,000+. Opening the kitchen to the living room, moving a bathroom wall, relocating plumbing within the unit, a new sub-panel or in-unit laundry. Needs engineering review, HOA architectural approval and city permits, and often a new sound-rated floor assembly. 3 to 5 months including approvals.
Line-item planning numbers for a Seattle-area rental unit
- Kitchen cabinets, installed: $5,000 to $12,000 for stock or RTA shaker cabinets in a typical 10-by-10 condo kitchen; $12,000 to $25,000 for semi-custom. Painting existing cabinets and adding new hardware costs $2,000 to $4,000 and is the single cheapest upgrade that photographs well in a listing.
- Counters: quartz or solid-surface runs $50 to $75 per square foot installed in the Seattle metro, so 30 to 40 square feet is $1,500 to $3,000. Laminate is roughly half that.
- Appliance package: rental-grade stainless (range, fridge, dishwasher, microwave hood) $1,800 to $2,800; mid-range $2,500 to $4,000.
- Bathroom: new vanity, faucet, toilet, mirror, light and exhaust fan with the tub reglazed, $3,500 to $7,000; a tiled tub surround or a tub-to-shower conversion adds $3,500 to $10,000.
- Flooring: LVP installed $5 to $9 per square foot including demo and transitions; add $1 to $3 per square foot for the acoustic underlayment most Seattle and Bellevue condo associations require over a neighbor. See our flooring cost guide.
- Interior paint: $3 to $5 per square foot of floor area for walls, ceilings, doors and trim in a vacant unit, so $2,500 to $4,500 for a 750-square-foot one-bedroom. Details in our interior painting cost guide.
- Electrical and plumbing repairs discovered during demo: budget a 10 to 15 percent contingency. Older Seattle condo buildings often turn up aluminum branch wiring, galvanized supply lines or polybutylene that the HOA requires you to replace when a wall is open.
- HOA and building costs: architectural review application $100 to $500, a refundable damage deposit, elevator padding and hallway protection, and sometimes a required building engineer's letter ($500 to $2,000) for any wall or plumbing change.
Why condos cost more per square foot than houses
A condo renovation touches the same trades as a house, but every one of them works slower. Materials and debris move through a lobby, an elevator and a corridor on the building's schedule, often only between 9 a.m. and 5 p.m. on weekdays. Water shutoffs for a kitchen or bathroom affect the whole stack and must be booked with the building manager. Hard flooring over another unit needs a sound-rated underlayment and often an IIC test or an approved product list. Garbage and recycling have to go into a licensed hauler's truck, not a driveway dumpster. Contractors publish condo projects running 15 to 30 percent longer than the same scope in a single-family home, and that time shows up in labor cost. The upside is that condos have no roof, siding, foundation or yard to surprise you, so the budget is far more predictable once the HOA rules are known.
What the HOA will ask for
Most Seattle and Eastside associations require written approval before any work beyond paint and furniture. Expect to submit a scope of work, drawings for anything structural or plumbing-related, your contractor's Washington license number, a certificate of insurance naming the association (general liability, usually $1 million, plus workers' compensation) and a construction schedule. Boards commonly meet monthly, so approval takes two to six weeks, and some buildings add a non-refundable review fee and a refundable damage deposit. Common rules: work hours limited to weekdays, no work on holidays, protective coverings in halls and elevators, a licensed and insured contractor only, hard flooring only with an approved acoustic underlayment, and no changes to windows, exterior doors, balconies or anything in a shared wall or chase. Blue Lake handles the submittal package for you and carries the insurance limits condo boards ask for.
Permits for condo work in Seattle and Bellevue
Paint, flooring, cabinets and like-for-like fixture swaps do not need a city permit. Any new or relocated plumbing, a new circuit or sub-panel, a moved wall, a new bathroom exhaust route, or in-unit laundry does. In Seattle, those go through SDCI as trade permits or a construction permit, and multifamily units get the commercial-building review path, which is slower than a house. In Bellevue, Kirkland, Redmond and the rest of King County, the city permit center issues plumbing, electrical and mechanical permits for the unit, and electrical permits in most of the state are issued by Washington Labor & Industries. Our Washington permit guide and the Seattle vs. Eastside permit timeline comparison cover what to expect.
Should you buy the materials yourself?
Many landlords ask for a bid that separates labor from materials so they can source cabinets, flooring, fixtures and appliances directly. It can work well, and we quote it regularly, with a few honest trade-offs. You take on ordering, lead times, deliveries and returns, and the schedule slips if a vanity arrives damaged or the LVP is backordered. Warranty on owner-supplied items is between you and the retailer, not the contractor. And the labor line usually rises a little because the crew is working around deliveries they did not plan. A good middle path for a rental unit: you pick and purchase the visible finishes you care about (cabinet style, counter color, flooring, fixtures, appliances) from an approved list with lead times checked, and the contractor supplies everything behind the walls plus drywall, paint, trim and disposal. Either way, insist on an itemized bid that shows labor, contractor-supplied materials, owner-supplied allowances, subcontractor costs, and permit and disposal fees as separate lines, which is exactly how Blue Lake writes every fixed-price contract. Our guides on comparing contractor bids and reading a remodeling bid explain what to look for.
Renovating a rental: how much is too much?
The right scope for a rental is set by the rent the unit can command, not by what you would want in your own home. Washington's 2025 rent stabilization law caps most annual increases for existing tenants at 7 percent plus inflation, with a 10 percent ceiling, and the state published a 9.683 percent cap for 2026, so the return on an upgrade mostly comes at turnover and from lower vacancy rather than from raising rent on a sitting tenant. Property managers in King County report that a $15,000 kitchen refresh adding $150 to $200 a month pays back in four to six years once faster leasing and fewer repair calls are counted. Upgrades that reliably move rent in Seattle and Bellevue: in-unit washer and dryer, a dishwasher where there was none, durable LVP instead of carpet, quartz counters, and good lighting. Upgrades that rarely pay in a rental: custom cabinetry, high-end tile, luxury appliances and layout changes that require structural work.
How long a condo renovation takes
Plan on two to six weeks for HOA approval before anything starts, one to three weeks for permits if plumbing or electrical moves, and then one to two weeks of construction for a cosmetic refresh, four to seven weeks for a landlord-grade full interior renovation and three to five months for a gut or layout change. Vacant units go fastest; working around a tenant adds dust protection, phased work and days when the crew cannot be there. Materials with long lead times (semi-custom cabinets, special-order appliances, quartz slabs) should be ordered before the HOA approval date so they arrive when demolition ends.
Working with an out-of-area owner
A large share of the condo and rental work we do is for owners who live outside Washington. The project runs on a written schedule with milestone dates, a weekly written update with photos, a single point of contact, change orders approved in writing before any extra work, and a final walkthrough by video call plus a punch list. Keys, lockbox and HOA move-in coordination are handled by us. If you want to stay involved in finish selections, we send sample photos and links for each decision with a response date so the schedule holds.
Before you ask for bids
- Get the HOA rules first. Request the renovation policy, approved flooring list, insurance requirements and work-hour rules before you price anything.
- Decide owner-occupied or rental. It changes the finish level, the appliance tier and whether layout changes make sense.
- Write the scope room by room. Kitchen, bath, flooring, paint, electrical, plumbing, trim, and "repairs found during demo" with an allowance.
- Ask for an itemized, fixed-price bid that separates labor, contractor materials, owner-supplied allowances, subcontractors, and permit and disposal fees.
- Confirm the license and insurance. Verify the contractor's Washington license on the L&I site and get a certificate of insurance that your HOA will accept; our guide on what a general contractor does explains what to check.
Frequently asked questions
How much does it cost to renovate a 1-bedroom condo in Seattle?
A landlord-grade full interior renovation of a one-bedroom condo (new kitchen, refreshed bathroom, LVP flooring, full paint) typically costs $28,000 to $50,000 in Seattle and Bellevue in 2026 when the layout and plumbing stay put. A cosmetic refresh runs $8,000 to $18,000, and a full gut with layout changes runs $75,000 to $150,000 or more.
Do I need HOA approval to remodel my condo?
Almost always for anything beyond paint and furniture. Most Seattle and Eastside associations require a written scope, contractor license and insurance certificate, and board approval, which usually takes two to six weeks. Hard flooring, plumbing, electrical and wall changes nearly always need approval.
Do I need a permit to remodel a condo in Seattle or Bellevue?
Not for paint, flooring, cabinets and like-for-like fixture replacement. Yes for new or relocated plumbing, new circuits or a sub-panel, moved walls, new exhaust routes or in-unit laundry, through SDCI in Seattle or the city permit center on the Eastside.
Can I buy my own materials and have the contractor bill labor only?
Yes. Blue Lake quotes labor and contractor-supplied materials separately when an owner wants to purchase finishes and appliances directly. You take on lead times, deliveries and product warranties, and we recommend keeping behind-the-wall materials, drywall, paint and disposal on the contractor's side of the bid.
Does Blue Lake work with out-of-state landlords?
Yes. We regularly renovate rental condos and houses for owners who live outside Washington, with a written schedule, weekly photo updates, written change orders, HOA coordination and a video final walkthrough. Every project is a fixed-price, itemized contract after a free on-site consultation.
Plan your condo or rental renovation
Blue Lake Construction is a licensed Washington general contractor (#BLUELLC760C3) based in Bellevue, renovating condos, rental units and investment properties across Seattle, Bellevue, Kirkland, Redmond, Sammamish, Issaquah, Mercer Island, Renton and Kent. See our whole-home remodel and investor flip page, our kitchen remodeling page and recent kitchen projects, our bathroom remodeling page, the kitchen remodel cost guide and bathroom remodel cost guide, or request a free consultation.
Subscribe to our Newsletter!

Subscribe to our Newsletter!

Latest Blog posts
View All

Blue Lake Construction
20.11.2026
8 min.
How Much Does a Laundry Room Remodel Cost in Seattle & Bellevue? 2026 Guide
2026 laundry room remodel costs for Seattle, Bellevue and the Eastside: cosmetic refresh vs full remodel, closet-to-laundry conversions, moving the laundry upstairs, line-item prices for plumbing, 240V dryer circuits, venting, cabinets and flooring, Seattle permit rules, timelines and resale value.

Blue Lake Construction
18.11.2026
8 min.
Tub-to-Shower Conversion Cost in Seattle: 2026 Walk-In Shower Guide
What a tub-to-shower conversion costs in Seattle, Bellevue and the Eastside in 2026: prefab vs. custom tile walk-in showers, curbless shower costs, plumbing and glass price factors, Seattle and Eastside permit rules, timelines, and aging-in-place design tips.

Not sure how to start? Get a free consultation.
One of our experts will get back to you as soon as possible.